Last reviewed: Thursday 18 Nov 2021 at 8.31am

Yeronga station is planned to reopen on Monday 13 December.

Construction activities will continue at the station until mid-2022, with station facilities (ticket office and machines, station canopies and shelter, pedestrian overpass, lifts, etc.) to open in stages.

Find out more about Cross River Rail's construction activity.

Timetable changes for Yeronga services

In August, changes were made to peak hour services on the Beenleigh line. Eight weekday services are currently running express from Yeerongpilly to Park Road, and won't stop at Yeronga (once reopened), Fairfield or Dutton Park stations. 

Make sure you re-plan your journey from Yeronga before you travel on Monday 13 December. 

Affected services